To the residents who park in 2005 Pleasant Valley’s garage,
The project has proceeded well. However, it has taken an extra day, because the vendor had to dig a few feet farther down than expected.
The remaining schedule currently appears to be:
Sat.-Sunday No work.
Monday: Fill in the pit in the driveway with the excavated dirt and repave the work area.
Tues.-Wed. No work.
Thursday: Pressure test with EBMUD Rep. present. Driveway will be unavailable until this test is completed. We anticipate midday. We believe this will be the end of the work.
We believe that only next Monday and Thursday will be days when the driveway is closed. Driveway closure hours will be from 9am to 5pm, although probably a shorter period of time on Thursday.
Sincerely, Manager